S.R. 0038 Section 259

Michael Kilgore

Before

Before

After

After

IMG_3535.JPG

Project Cost: $862,651
Client: PennDOT District 10-0
Contact: Doug Zubal, P.E.
Project Letting: December 2017

S.R. 0038, Section 259 is located in Concord Township, Butler County.  The project consists of the replacement of the reinforced concrete arch culvert that carries SR 0038 over a tributary to Connoquenessing Creek with a precast reinforced concrete box culvert.  The horizontal and vertical alignment match the existing roadway. Minimal roadway approach work was included for approximately 200 feet on the western approach and 250 feet on the eastern approach. One lane of traffic was maintained throughout construction of the project via half-width construction, controlled with temporary traffic signals.   

 

S.R. 0322 Section 554

Michael Kilgore


Cost: $1.02 million
Client: PennDOT District 10-0
Contact: John McCombie, P.E. (724-357-2964)
Project Letting - August 2016


Arch Culvert Extension and Rehabilitation, This project consisted of the extension, both upstream and downstream, and rehabilitation of a reinforced concrete arch culvert (10’ span) carrying S.R. 0322 over a Tributary to Coder Run. Access and constructability were the primary challenges associated with this project. The scope of work also included 850’ of approach roadway reconstruction. 

 

Back

S.R. 1006, Section 450

Michael Kilgore

After

After

After

After

Cost: $3.04 million
Client: Engineering District 10-0
Contact: Mr. Jason Layman (724-357-7614)
Project Letting: August 2014

Indiana County - This project included the phased total replacement of a deteriorated four span steel girder bridge with inadequate underclearance with a two span continuous fabricated steel girder bridge (230’ total length) with minimal profile grade adjustment. The bridge carries S.R. 1006 (Airport Road) over four lanes of S.R. 0119. The project also included 370’ of approach roadway reconstruction.